WTP Shindetekdi

Civil, finishing and site works at the water treatment plant on Shinde Tekdi, Malinagar, Vadgaon — brickwork, plaster, painting, aerator coating, flooring, drains and fencing, photographed on site from October 2025 to February 2026.

Work at the WTP Shindetekdi site covered the main plant building, its elevated walkway and tower, the aerator bowl and the ground around them — taken from brickwork under scaffolding through to a painted, fenced and finished plant.

The building and tower were first completed in brick masonry and plastered outside. The aerator bowl was cured with water and later given a blue protective coating. Around the plant, block masonry drains and steps were built and the floor was finished with a power trowel.

In the final stage the exterior was primed and painted, perimeter fencing was put up, and the site was handed over clean with its gate in place.

Dates below come from the GPS-stamped site photos taken between 20 October 2025 and 7 February 2026.

Work stages

How the work progressed.

  1. 0120 Oct 2025

    Brickwork under scaffolding

    Main building, walkway and tower in brick masonry, with scaffolding around the tower.

  2. 026 – 22 Nov 2025

    External plaster

    The tower and main building were plastered outside, working down from the scaffolding; stair and walkway plaster followed.

  3. 0315 Nov 2025

    Aerator bowl curing

    The stepped aerator bowl was kept wet to cure before any coating.

  4. 0423 Nov – 11 Dec 2025

    Site works & drains

    Ground work around the plant, then block masonry drains and steps along the building.

  5. 0516 Dec 2025

    Primer & flooring

    White primer went on the exterior and the concrete floor was finished with a power trowel.

  6. 061 Jan 2026

    Night check

    The building was photographed at night with its external lights on.

  7. 0716 – 17 Jan 2026

    Aerator coating

    A blue protective coating was applied to the aerator bowl.

  8. 0818 – 24 Jan 2026

    Fencing & final paint

    Fence posts and wire went up around the plant while the final exterior colour was applied.

  9. 097 Feb 2026

    Completed

    Plant building, walkway and tower finished, with perimeter fencing and the gate in place.

Before & after

From site work to finished structure.

Drag the handle to compare the same spot during work and after completion.
WTP Shindetekdi: Main building and walkway after completion, with fencing and gate
WTP Shindetekdi: Main building and walkway during brickwork and scaffolding
Before· 20 Oct 2025After· 7 Feb 2026
Main building & walkway
WTP Shindetekdi: Main building front after painting and fencing
WTP Shindetekdi: Main building during plastering
Before· 15 Nov 2025After· 7 Feb 2026
Main building — front view
WTP Shindetekdi: Tower and circular platform after completion
WTP Shindetekdi: Tower and circular platform under scaffolding
Before· 6 Dec 2025After· 23 Jan 2026
Tower & circular platform
WTP Shindetekdi: Aerator bowl after blue protective coating
WTP Shindetekdi: Aerator bowl being cured before coating
Before· 15 Nov 2025After· 16 Jan 2026
Aerator bowl — protective coating

Gallery

On site.

Start a conversation

Have a construction or infrastructure requirement?

Share your requirement — we’ll get back to you with the next steps.

Prefer to talk? Call +91 83790 62127

Chat with Swarajya Enterprises on WhatsApp